We are in agreement with builders Road of the Future

We are in agreement with builders Road of the Future

Tech May 17, 2017 15:36

oss - The municipality of Oss has a claim for damages from the two road builders for 3.3 million euros. The municipality reported this to the city council.

The Road of the Future is a prestigious project of the municipality of Oss and the province of North Brabant, which has cost more than 80 million euros in total. But since delivery, attention is only focused on problems. LED lights in the berm that drivers must literally bring in a green wave over five crossings do not work and the luminous lineage made no impression.

Contractors Ballast Nedam and Van Gelder claimed a million claim due to additional costs due to weakening. Based on the outcome of an arbitration case, a settlement has been paid from the available project budget, according to the municipality of Oss. The municipality does not expect any further deficiencies anymore.

Leave a comment

The HOTRECENTNEWS.com is not responsible for the content of external sites.

SEARCH

Back to Top